The Heavy Lifting Work of the HIDW Project in Rus
On the afternoon of January 28th, local time, the last equipment- HDT sewage stripping tower T-1 of the HIDW Complex Pr
On the afternoon of January 28th, local time, the last equipment- HDT sewage stripping tower T-1 of the HIDW Complex Pr
Russia Lukoil DCU Project received a letter of commendation from the owner Lukoil (Lukoil Holdings) on February 12th, t
At 15:20 pm on January 22nd, local time, the final layer concrete casting of the three silo structures for the 8-14 axi
On the morning of January 16th, with the roar of several excavators, the foundation of the PR101 pipe rack in the synth
The Pipeline attached to C3 Separation Tower of RFCC in Nigeria Dangote Oil Refining Project was Hoisted in Place The e
At 2:00 pm on January 6th (local time), heating furnace H-201 was successfully ignited in one time in Russian Deep Conv
On December 22nd, the first bridge erecting machine of Dubai R1013 Road and Bridge Project successfully passed the perf
On December 21st, the comprehensive house, auxiliary house, guard room, vent area, fire pump station area and plant roa
At 22:00 on December 21st (local time), in the outdoor temperature of nearly minus 30 degrees Celsius, a heavy equipmen
On November 29th, a commencement ceremony was held for the second phase of Hainan Fine Chemical Project in the construc