Chongqing BASF project (Comprehensive professional construction) main body frame had been completed in advance

Release time: 2013-05-16  Browse: 5382

 

On March 21, Chongqing BASF project aniline device area C260 concrete frame had been capped successfully; this means that Chongqing BASF MDI project (Comprehensive professional ) civil work main body frame built by our company had been completed in advance.
 
Up to march 21, monolayer concrete frame of Pyrolysis device(C245), 3 layers concrete frame of sewage tower device (C210), 4 layers concrete frame of MNB device (C230), 3 layers concrete frame of aniline device C260of this project all had been completed in good quality, safety and successfully. And owner’s construction period goal had been completed in advance. This had made a good construction situation and precious time for the following installation work.
 
At capping site, project leaders such as project manager Shao Chengwang, construction manager Xiao Zhenyang had been warm congratulated and praised by Owner and manage company leaders; they also praised project staff’s giving and effort in earlier civil work .