The Main Structure of the Silo in Russian Lukoil DCUProject was Successfully Capped

Release time: 2021-02-10  Browse: 8331

At 15:20 pm on January 22nd, local time, the final layer concrete casting of the three silo structures for the 8-14 axis of the 210A silo in Russian Lukoil DCU project completed means that the structure was successfully capped. So far, the concrete structures of the six silos of the project have all been capped, and the total concrete pouring volume is about 1900m3. Due to the special structure of the silo and site restrictions, the hydraulic self-hoisting form turn over RCS system designed by the German PERI-UP company was used for the construction. With a tight schedule, heavy tasks, and difficult winter construction, all team members of the project have not flinched but tackled the difficult head on with wisdom and perseverance, and work tirelessly for the smooth completion of the project.