The water testing of the first storage tank of Chongqing BASF project has been succeeded

Release time: 2014-03-19  Browse: 950

 

On January 14, Chongqing BASF B310 tank area TK9555 was taken filling water test which is the first water test storage tank of Chongqing BASF project. On 18th Jan., TK9555 storage tank pressure test has been completed successfully.
Since construction was started at March 2013, 70% of all storage tank construction has been completed by Chongqing BASF project; main part and pipeline of 11 storage tanks in B300 area has been completed; main part of C300 will been completed after spring festival. At present, all staff of Chongqing BASF project was constructing in accordance with Owner’s high quality and high standard to attain Owner’s specified goal.