The first large equipment of Russia TAF project had been hoisted successfully

Release time: 2013-08-13  Browse: 5406

 

On 3th August, 13:56 Russia local time, under the commander commanded, urea synthesis tower, the first large equipment of Russia TAF, had been hoisted officially. After 1 hour, this equipment had been hoisted in position, meaning the hoisting work of large equipment of Russia TAF project would be started officially. the weight of this equipment is 308t. one 750t crawler crane was used as main crane; one 350t crawler crane was used as auxiliary crane by project department. The radiusof hoisting work is 20m, hoisting load rate is 79%.
The success of first hoisting of large equipment has won accordance good reputation of Owner, inspector and combo. August and September are fastigium of equipment hoisting of TAF project. According to 2013 whole plan requirement, project department would organize machines and tool and manpower reasonably to finish following hoisting task successfully.
(文/黄伦川)